SERVICE CONTRACT (SAMPLE FOR TESTING) 8.2 Rectification. The Contractor shall rectify defects notified by the Employer within 30 days of notification. Extensions of this period only by written variation signed by both parties. 15.1 Delay damages. Where the Contractor fails to complete on time, delay damages of 0.5% per week of the affected item value apply, capped at a maximum of 10% of the contract value. 11.3 Defects liability. The defects liability period is 24 months from the date of taking-over. Fair wear and tear and damage caused by misuse by the Employer's personnel are excluded.